Construction Update – July 2018 for 100 Main

0
1151

Hello neighbor. The Streetlights Residential Construction Team is very excited to be a part of this
community and develop this wonderful project that will bring in new residences and businesses soon.
Our goal is to be a good neighbor to the community, foster relationships, and partner with you during
the construction process. Our Monthly Construction Update will keep you informed of pertinent
activities that may have an effect of vehicular traffic patterns and pedestrian re- direction.
We are aware of the parking sensitivity and have instructed our workers to park in areas away from
businesses. Our number one priority is public safety.
The month of July will see the following activities:
· Pile driving activities will conclude this month
· Caisson drilling
· Continued excavation of parking garage through mid-August
· Mass soil hauling through mid-August
The staging area for our trucks is located on the Cal Trans lot on the south side of Highway 78 so trucks
will not be idle on the streets surrounding the projects. However, due to logistics, the City has granted a
half-street closure of Indiana in the southbound direction (project side) so trucks may enter and exit the
site. The northbound lane remains open 24/7 for access to access to Vista Village including the adjacent
public parking lot. This is only a daily closure, so the street will re- open at the end of the work day.