Grand Avenue Vision Project Update

0
573

Grand Avenue is undergoing construction improvements! On January 10, 2022, the City began the Phase 1 construction of the Grand Avenue Vision Project.

Starting this week, existing light posts will be removed and minor concrete work will be performed from Maple to Kalmia Street. The contractor will start drilling for new light post foundations; this work is expected to be done at night.

Starting next week, the contractor is expected to pour the concrete curb, gutter, and light post foundations.

Learn more and sign up for updates at: escondido.org/grand-avenue-vision-project