Construction is underway on the next phase of the Paseo Santa Fe Street Improvement Project. Crews will begin at Oceanview Drive and work toward Civic Center Drive.
If you are driving North you will not be able to turn left on to Guajome St. This is the last time you will see traffic on the west side of Santa Fe unit 2020
Sewer mains will be constructed first, then storm drain facilities and water lines, followed by the undergrounding of overhead utility lines
Surface improvements such as landscaping, sidewalks, and lighting will be completed during the final segment.
South Santa Fe Avenue
•Traffic control will be installed and will extend from Oceanview Drive to just south of Terrace Drive.
•The traffic control will shift traffic to the east on the S. Santa Fe Avenue, while maintaining two-way traffic.
•Work will take place along the west side of the street. Parking will be restricted in this area.
•Access to entry ways will be maintained.
The construction is expected to be completed in March, 2020.